If your gas installation permit includes appliances that require Commissioning Approval (CA), you may have questions about when approvals are required, how invoices are generated, and why final inspection may still be unavailable. The following answers address some of the most common questions.
Each appliance that requires Commissioning Approval must have its own CA request. If a permit includes multiple appliances that are subject to Commissioning Approval requirements, a separate CA request must be submitted for each qualifying appliance.
Whether a Commissioning Approval is required depends on the appliance type and characteristics. Refer to the Commissioning Approval Information Bulletin or the regulation requirements described below for details.
Example
|
Appliance |
Quantity |
CA Submission Required? |
Number of Invoices |
|
Water Heater (100,000 BTU) |
2 |
No |
None |
|
Direct-Fired Makeup Air Unit (200,000 BTU) |
1 |
Yes |
1 |
|
Boiler (600,000 BTU) |
2 |
Yes |
2 |
In this example:
Final inspection will not become available until Commissioning Approval requests have been submitted for all qualifying appliances on the permit.
Common reasons why final inspection remains unavailable include:
After all required Commissioning Approval requests have been submitted, it may take a few minutes for Final Inspection to become available. If Final Inspection is still greyed out, try:
If the issue persists, please contact us.
Invoices are generated the day after a Commissioning Approval request is submitted.
This means that you do not need to wait for an invoice to appear before requesting a final inspection. Final inspection becomes available once all required Commissioning Approval requests have been submitted.
In some cases, additional information about an appliance may be needed to determine whether a Commissioning Approval is required. For example, certain appliances that exceed the BTU threshold may not meet all of the criteria requiring Commissioning Approval.
If you believe a CA should not apply to your appliance, please contact us for further review.
Commissioning Approval requirements are established under the Gas Safety Regulation.
Certain gas appliances must receive Commissioning Approval before being placed into service. Commissioning Approval requests must be submitted at least 48 hours before these appliances are put into operation.
For more information on gas Commissioning Approval requirements, review our information bulletin.